Smarter Heating & Hot Water

Boilers

Boiler Plus

Boiler Plus is the set of minimum standards for fitting a gas boiler in an existing home in England. It started on 6 April 2018. Since 15 June 2022 it has been part of Approved Document L, alongside some newer rules on controls, sizing and commissioning.

The idea behind Boiler Plus was simple: when a gas boiler goes in, it should be an efficient one, it should have proper controls, and a combi should come with one extra energy-saving measure. It was introduced by the then Department for Business, Energy & Industrial Strategy and is enforced through Part L (conservation of fuel and power) of the Building Regulations.

Boiler Plus is an England rule. Wales, Scotland and Northern Ireland have their own Building Regulations. Your installer should work to the rules for the country the home is in.

What Boiler Plus requires

The four options for a gas combi

Measure What it does
Flue gas heat recovery A device that pre-heats the incoming cold water for hot water using heat recovered from the boiler’s flue. Some boilers have it built in; others take a separate unit. Check compatibility with the boiler maker.
Weather compensation Measures the outdoor temperature (an outside sensor, or with some controls, local weather data from the internet) and lowers or raises the boiler flow temperature to match.
Load compensation Varies the flow temperature based on how far the room is from the thermostat setting. It usually replaces the room thermostat and needs no extra sensor.
Smart thermostat with automation and optimisation A room thermostat that gives time and temperature control, adjusts its schedule automatically (from your settings or by detecting occupancy), starts the boiler at the right time to reach temperature (optimum start), and can be adjusted remotely.

Weather and load compensation can work by modulating the boiler, which needs a protocol such as OpenTherm or the maker’s own bus, or by switching the boiler on and off in a way that changes the flow temperature. Modulating control is usually the better choice. A plain on/off “smart” thermostat only counts if it has all of the smart functions listed above.

What changed in 2022

From 15 June 2022 the 2021 edition of Approved Document L, Volume 1 (Dwellings) replaced the old Domestic Building Services Compliance Guide in England. The Boiler Plus rules carried over, and these were added or tightened for gas boiler work:

Oil boilers have their own minimums under the same document: 91% efficiency, or 86% for an oil combi.

Who is responsible

Gas boiler work in the UK must be done by a Gas Safe registered engineer. In England, the engineer notifies the job through Gas Safe’s competent person scheme. You should then get a Building Regulations Compliance Certificate. Keep it, because buyers’ solicitors usually ask for it when you sell.

Both the person doing the work and the property owner are responsible for meeting the Building Regulations. Building control can require non-compliant work to be put right, and it can lead to prosecution. Older articles quote a £5,000 maximum fine. That cap no longer applies, because fines for this offence in England and Wales have been unlimited since 2015. In practice, the simple protection is to use a Gas Safe engineer and check that the controls and extra measure on your quote meet the rules.

Questions to ask on a quote

  1. What is the boiler’s ErP seasonal efficiency?
  2. If it is a combi, which of the four Boiler Plus measures is included, and is it a modulating control?
  3. Will there be TRVs or other room-by-room control in every room except the one with the room thermostat?
  4. Has a heat loss calculation been done, and what output will the boiler be set to?
  5. Will the system be flushed and dosed with inhibitor, and the Benchmark checklist filled in?

Related

Guidance only, updated from the original hub.myboiler.com Boiler Plus page (2018) and checked against the 2021 edition of Approved Document L, Volume 1, and BEAMA’s Part L heating controls guidance. It covers England. For the exact rules on a job, use the current Approved Document and the boiler and control makers’ instructions.